High Mast Commissioning & Acceptance Checklist (Tender-Ready)

Onde este guia se encaixa

Acceptance Deliverables (Pass/Fail)

  • Photometrics pack: IES/LDT + final layout + assumptions + results tables (Avg/Min/Uniformity)
  • As-built drawings: pole, base plate, anchor bolts, wiring, accessories, aiming notes
  • Commissioning checklist: electrical checks, aiming verification, protection devices, functional tests
  • O&M pack: maintenance schedule, lowering device instructions (if used), spare parts plan
  • Warranty & SLA: scope, response time, RMA workflow, replacement lead time

Copy/Paste Commissioning Checklist

  • Verify installed pole height and mounting arrangement vs approved layout
  • Verify aiming/tilt limits and any glare shields/visors installed
  • Record electrical protections (SPD, grounding), circuit labeling, and test results
  • Record luminaire IDs / batch references (traceability)
  • Capture commissioning photos (key views + identifiers)

RFQ clause (copy/paste)

  • Supplier/installer must provide a commissioning checklist and acceptance record set as a deliverable.
  • Final handover must include as-built drawings, photometrics pack, O&M pack, and warranty/SLA documents.