PIR vs Time Dimming for Solar Street Lights — Energy, Reliability & Procurement Rules
Dimming is the hidden variable that breaks quote comparisons. Two lights with the “same wattage” can have totally different real energy use depending on the dimming profile. This guide explains PIR vs time-based dimming in a procurement-ready way: how to compare, what risks to watch, what to record during commissioning, and how to write RFQ clauses so bids become apples-to-apples.
Dónde encaja esta guía
- Comience aquí: Centro de información para compradores
- Páginas relacionadas del sistema: Farolas solares todo en uno, Farolas solares decorativas
- Centros de evidencia: Definiciones de especificaciones · IES/DIALux · Evidencia de calidad
Resumen (Reglas de decisión)
- Time dimming is predictable. It is easier to model (Wh/night) and easier to compare quotes fairly.
- PIR dimming can save energy in low-traffic areas, but requires clear assumptions (base vs boost time) and reliable sensor placement/commissioning.
- Norma de contratación: any bid without a declared dimming profile (or PIR assumptions) is Not Comparable.
- Commissioning rule: dimming mode and settings must be recorded; otherwise warranty and troubleshooting become un-auditable.
Referencias internas clave:
- Cálculo de los días de autonomía (Wh/noche)
- Tallas para la temporada de lluvias (mes más lluvioso)
- Lista de verificación para la instalación y puesta en marcha
- Compara cotizaciones (en condiciones equivalentes)
Definiciones (adaptadas a la contratación pública)
Time dimming (schedule-based)
The light follows a fixed schedule after dusk (e.g., 100% for 2 hours, 50% for 6 hours, 30% until dawn). It is predictable and easy to model in the energy budget sheet.
PIR dimming (motion-based)
The light runs at a base level (low power) and boosts to a higher level when motion is detected. Energy depends on traffic: how often motion triggers and how long boost stays on.
Why this matters for solar sizing (Wavg is everything)
Solar sizing is driven by average power (Wavg) over the night. Wavg drives:
- Daily energy use (Wh/night)
- Battery required usable energy
- PV required charging yield (especially worst-month)
Use these sizing pages as the “math backbone”:
Time dimming: strengths, risks, and where it fits
Strengths
- Predictable energy: easiest to calculate and audit (Wh/night).
- Quote comparability: suppliers can be forced to use the same schedule.
- Commissioning simplicity: fewer variables than PIR traffic assumptions.
Risks
- If the schedule is not documented, site teams cannot confirm Wavg assumptions.
- “Too aggressive” dimming can create user complaints if brightness drops too early.
Best-fit use cases
- Main roads where predictable performance is required
- Projects where bid comparability and auditability are critical
PIR dimming: strengths, risks, and where it fits
Strengths
- Potential energy savings in low-traffic zones (parks, pathways, rural roads).
- Can improve perceived “responsiveness” when someone approaches.
Risks (what breaks projects)
- Hidden assumption risk: savings depend on motion frequency and boost duration.
- Sensor placement risk: wrong mounting/angle can miss motion or false-trigger.
- Commissioning complexity: sensitivity and boost settings must be recorded.
- Comparability risk: two suppliers can claim the same autonomy with totally different PIR assumptions.
Best-fit use cases
- Low-traffic areas where energy saving is a primary goal
- Sites that can accept variable energy behavior (depends on motion)
Apples-to-apples comparison method (mandatory for procurement)
To compare quotes fairly, you must force suppliers to use a declared, comparable dimming model.
Option A (recommended): compare with the same time-dimming schedule
- Define one schedule (Scenario A) and require all suppliers to quote against it.
- This creates clean Wh/night comparability across bids.
Option B (if you must use PIR): require a PIR assumption disclosure
Require the supplier to disclose these PIR assumptions in the quote:
- Base level (percentage or watts)
- Boost level (percentage or watts)
- Boost duration (seconds/minutes)
- Assumed motion events per hour (or per night) used to model Wavg
- Sensor range and mounting orientation assumption
Norma de contratación: if PIR assumptions are not disclosed, the quote is Not Comparable.
Use this page to enforce bid comparability:
Commissioning and acceptance (dimming must be recorded)
Commissioning record requirements
- Dimming mode used (time / PIR / hybrid)
- Schedule steps (time dimming) OR base/boost/sensitivity settings (PIR)
- Runtime intent (dusk-to-dawn or fixed hours)
- Any later setting change must be logged (date + reason)
Use the operational template here:
Failure patterns linked to dimming (field diagnosis)
- Early shutoff after cloudy weeks: Wavg higher than assumed OR worst-month sizing deficit.
- Complaints about “too dark”: schedule too aggressive OR PIR base level too low.
- Random behavior: loose connections, ingress, or configuration not standardized.
Referencia:
Normas de contratación de tipo «aprobado/rechazado»
Marcar una puja SUSPENSO (No comparable) si falta:
- Dimming mode disclosure (time / PIR / hybrid)
- Time schedule steps OR PIR base/boost/boost-time assumptions
- Hoja de balance energético (Wpromedio, horas de funcionamiento, Wh/noche)
- Plantilla de registro de puesta en servicio (los ajustes deben ser auditables)
Copy/Paste RFQ Clauses (PIR vs Time Dimming)
Clause 1 — Dimming profile disclosure (mandatory)
Supplier shall disclose the dimming method (time/PIR/hybrid) and the exact dimming profile used for sizing and quotation. Quotes without a declared dimming profile are not comparable.
Cláusula 2 — Hoja de balance energético (obligatorio)
Supplier shall provide an energy budget sheet including Wavg, runtime hours, and Wh/night based on the declared dimming profile.
Clause 3 — PIR assumptions disclosure (if PIR is used)
If PIR dimming is used, supplier shall disclose base level, boost level, boost duration, and assumed motion event frequency used to model average power (Wavg). Supplier shall also disclose PIR sensor range and mounting orientation assumptions.
Clause 4 — Commissioning record (mandatory)
Supplier/contractor shall provide a commissioning record template and deliver commissioning settings (mode + schedule or PIR settings) as part of handover. Any settings change shall be logged with date and reason.
Request Dimming Profile & Energy Budget Templates
Get the editable templates used to standardize dimming assumptions and prevent non-comparable bids:
- Time-dimming schedule template (Scenario A/B/C)
- PIR assumptions disclosure sheet (base/boost/boost-time/events)
- Energy budget sheet template (Wavg, hours, Wh/night)
- Plantilla de registro de puesta en servicio (modo + ajustes)
¿Quieres una rápida verificación de la viabilidad técnica?
Indique la clase de vía, la altura del poste, los valores objetivo de lux y uniformidad, y las hipótesis de PSH para el mes más desfavorable.
Próximos pasos (mantenga su proyecto listo para la licitación)
Asegúrese de que su proyecto de alumbrado público solar cumpla con todas las normas de contratación y de ingeniería.
Plantillas y pruebas
- 📑 Centro de información para compradores — Elige un escenario y sigue el enfoque basado en la evidencia.
- 📊 Biblioteca de recursos — Especificaciones, pruebas de control de calidad y flujos de trabajo IES.
- 🔍 Centro de definiciones de especificaciones — Normalizar los datos de Wavg, Wh e IP/IK.
- 💡 Centro IES & DIALux — Validación del espaciado y la uniformidad.
- 🛡️ Control de calidad — Pruebas contrastadas frente a afirmaciones de marketing.
- 📋 Kit de solicitud de cotización y presupuesto — Plantillas, cláusulas y rúbricas de calificación.
Seleccionar un tipo de sistema
- 🚀 Farolas solares todo en uno
- 🌓 Farolas solares «todo en uno»
- 🛠️ Farolas solares tipo dividido
- 📏 Farolas solares
- ✨ Farolas solares decorativas
- ⚠️ Soluciones específicas (A prueba de explosiones/Híbrido)
Preguntas frecuentes
Which is better: PIR or time dimming?
Time dimming is better when predictability and bid comparability matter (roads and critical projects). PIR can save energy in low-traffic areas if assumptions are disclosed and commissioning is done properly.
Why do PIR quotes often look “too good”?
Because savings depend on assumed motion frequency and boost duration. Without disclosed assumptions, the energy model cannot be audited, so the quote is not apples-to-apples.
What must be recorded at commissioning?
The dimming mode and exact settings (schedule steps for time dimming, or base/boost/sensitivity/boost-time for PIR) plus any later changes with date and reason.
