RFQ / BOQ Must-Haves for Solar Street Lights — Tender-Ready Checklist

Where This Guide Fits

TL;DR (Tender rules you should enforce)

  • Lock comparability: require IES + simulation, declared dimming profile, energy budget sheet (Wavg/Wh-night), and worst-month sizing check.
  • Stop “Ah-only” battery traps: require battery in Wh + usable energy policy + BMS protections list.
  • Lock configuration: no silent substitutions for sealing-critical parts (gaskets, vents, connectors), optics, LED/driver, and battery pack.
  • Make it enforceable: require traceability (serial → QC records) + commissioning record templates + warranty SLA + spares plan.

RFQ vs BOQ (simple definitions)

  • RFQ = requirements + evidence + acceptance + commercial terms (what must be true).
  • BOQ = bill of quantities + itemized deliverables (what is included, how many, and what documents/services come with it).

RFQ Must-Haves (copy/paste structure)

1) Project scope & application

  • Road type and use case (urban, rural, highway, pedestrian path)
  • Target lighting intent (refer to local authority/spec, not “looks bright”)
  • Operating environment (dust, coastal, flood-prone, vandal risk)

2) Lighting performance requirements (make photometrics mandatory)

  • IES file required for the quoted optic
  • Simulation PDF required using your declared layout inputs (height/spacing/offset/arm/tilt)
  • Declared CCT/CRI and beam/optic type basis
  • Delivered lumens for the quoted configuration (not chip lumens)

Reference guides:

3) Energy model requirements (stop hidden sizing assumptions)

  • Dimming profile disclosure (time/PIR/hybrid + steps)
  • Energy budget sheet: Wavg, runtime hours, Wh/night
  • Worst-month/rainy-season sizing sanity check consistent with the energy budget

Reference guides:

4) PV, controller, and charging requirements

  • PV module model + datasheet + physical dimensions
  • Controller type disclosure (MPPT or PWM) + charging assumptions disclosure

Reference guides:

5) Battery requirements (make Wh and protections mandatory)

  • Battery capacity in Wh (nominal voltage + Ah or direct Wh)
  • Declared usable energy policy (usable factor + low-voltage cutoffs)
  • BMS protections list (over-charge/over-discharge/over-temp/over-current + balancing policy)

Reference guide:

6) Durability: IP/IK and corrosion control

  • IP/IK ratings for the assembled product in the delivered configuration
  • Configuration disclosure for sealing-critical parts (gaskets, vents, connectors, glands)
  • No silent substitutions policy for sealing-critical components

Reference guide:

7) Quality evidence, traceability, and no-silent-substitution

  • Serial number system linking unit → key components → QC records
  • QC checkpoints disclosed (incoming/inline/final)
  • No silent substitutions (optics, LED/driver, battery pack, sealing-critical parts)

8) Installation, commissioning, and acceptance

  • Commissioning record templates (layout inputs, dimming settings, serial-to-location mapping)
  • Acceptance checklist and photo evidence requirements (connectors/glands/lens seating where applicable)

Reference guide:

9) O&M, spares, and warranty (make support measurable)

  • Warranty scope (lamp, battery/BMS, controller, PV) and exclusions
  • Warranty claim evidence list and workflow
  • SLA (response/diagnosis/dispatch)
  • Spares plan (recommended spare ratio and lead time)

Reference guides:


BOQ Must-Haves (itemize deliverables so scope can’t be “shrunk”)

BOQ Line ItemMinimum DeliverableNotes
Solar street light unitsQty + exact model/configurationLock optics, CCT/CRI, dimming mode
PV module(s)Model + datasheet + dimensionsFit & mounting plan required
Battery packWh rating + BMS protectionsUsable policy + cutoffs disclosed
ControllerMPPT/PWM declaredCharging assumptions disclosed
Poles / brackets (if included)Qty + dimensions/specWind/load considerations
DocumentsIES + simulation + energy budget sheetRequired for acceptance
Commissioning deliverablesSettings + mapping + photosWarranty enforceability
Training / handoverBasic O&M handover packOptional but recommended
SparesSpare plan + lead timeAvoid long downtime

PASS/FAIL screening (use before scoring price)

Mark a bid FAIL (Not Comparable / High Risk) if it lacks any of these:

  • IES file + simulation PDF using your declared layout inputs
  • Dimming profile disclosure + energy budget sheet (Wavg/Wh-night)
  • Worst-month/rainy-season sizing sanity check
  • Battery in Wh + usable energy policy + BMS protections list
  • IP/IK assembled-product declaration + sealing-critical configuration disclosure
  • Warranty SLA + claim evidence workflow + traceability commitment


Request RFQ/BOQ Tender Toolkit

This toolkit helps you issue a clean tender that produces comparable bids and enforceable warranties:

  • RFQ specification template (evidence pack + acceptance gates)
  • BOQ itemization template (scope lock)
  • Bid PASS/FAIL checklist (before price scoring)
  • Warranty SLA & claim evidence checklist

Want a quick engineering sanity check?

Share your road class, pole height, target lux/uniformity, and worst-month PSH assumptions.

Next Steps (Keep Your Project Tender-Ready)

Ensure your solar street light project meets all procurement and engineering standards.

Templates & Evidence

FAQ

Why do solar street light tenders fail even with “good brands”?

Because the RFQ allows hidden assumptions. Without IES + simulation, energy budget sheets, worst-month checks, and evidence-based warranty terms, bids are not comparable and failures become disputes.

What is the single most important RFQ deliverable?

The evidence pack: IES + simulation + energy budget sheet (Wavg/Wh-night) + worst-month sizing sanity check, tied to declared dimming and component specifications.

How do I stop silent substitutions after award?

Lock configuration in the RFQ (optics, sealing-critical parts, battery pack, controller type) and require traceability (serial-to-QC records) plus approval for any change.